LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays

Photo: NST. The long-delayed LRT3 Shah Alam Line is now expected to begin operations by June 2026, with final testing currently underway, Transport Minister Anthony Loke confirmed in the Dewan Negara.
The 37.8km rail line, connecting Bandar Utama in Petaling Jaya to Johan Setia in Klang, will feature 25 stations and key interchange points at Bandar Utama (MRT Kajang Line) and Glenmarie (LRT Kelana Jaya Line).
"Once operational, it is projected to serve around 67,000 commuters daily, improving connectivity across Petaling Jaya, Shah Alam and Klang," Loke said.
However, before trains can start carrying passengers, several technical hurdles must be cleared. The delay, Loke stressed, is not due to cost-cutting measures but unresolved signalling and system stability issues discovered during fault-free run (FFR) testing and commissioning.
"So far, 14 out of 22 train sets have completed trials, with the remainder still undergoing testing. After all trains pass the FFR stage, the Land Public Transport Agency (APAD) will conduct final inspections before approval for operations," he added.
The project’s timeline has shifted multiple times. It was initially slated to open in September 2024, then pushed to December 2025, and now June 2026 following software and system-related issues identified during testing.
Beyond delays, LRT3 has also faced scrutiny over its rising cost. Launched in 2016 with an initial price tag of RM9 billion, the figure later ballooned to RM31.7 billion after previously excluded costs including consultancy fees, operational expenses and interest during construction.
In 2018, the government revised the scope, shelving five stations and cancelling one, which brought the cost down to RM16.63 billion.
Subsequently, five stations which consist of Tropicana, Raja Muda, Temasya, Bukit Raja and Bandar Botanik were reinstated, adding RM5.3 billion to the project and bringing the total cost to RM21.93 billion.

As for accountability, the project carries liquidated ascertained damages (LAD) of RM2.73 million per day for delays, equivalent to 0.024% of the total contract value.
The main contractor, Setia Utama LRT3, a unit of Malaysian Resources Corporation Berhad (MRCB) will be responsible for the compensation, although the final amount will only be determined once the project is fully completed.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRS2271
SELANGOR
BSU1401
JOHOR
JF384J
PULAU PINANG
PSF9490
PERAK
APL8039
PAHANG
CFH8716
KEDAH
KGJ3035
NEGERI SEMBILAN
NEM1410
KOTA KINABALU
SJU3520
KUCHING
QAB6589P
Last updated 30 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Forget Luxury Condos! PM Anwar Wants Affordable Homes Next To Train Stations – Here’s The Plan
PM Anwar wants affordable homes, not luxury condos, next to LRT3 stations! See the 4 locations identified for new Transit-Oriented Developments in the Klang Valley.
30-06-2026
LRT3 Shah Alam Line Expected To Open In June
After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.
05-02-2026
Prasarana Ridership Jumps 11% in 2025
Prasarana ridership jumps 11% in 2025 hitting 1.31 million users.
07-01-2026
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
LRT3 Might Be Delayed Again As Testing Encounters Issues - Report
The LRT3, expected to open early next year, may face further delays due to ongoing signalling system issues.
07-12-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
LRT3 Will Begin Operations On Sept 30 - Loke
LRT3 will begin operating on September 30 this year, Transport Minister Anthony Loke announced.
27-02-2025
Latest News
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
Malaysia's First Locally Built EV And PHEV Pick-Ups Are Coming From JAC
JAC will locally assemble its T9 EV and PHEV in Kulim, creating Malaysia's first CKD electrified pick-ups, with exports also being explored.
29-09-2026
Nearly Half A Million Summonses To Foreign Drivers: JPJ Says Some Employers Are Enabling It
JPJ issued 481,119 summonses to foreign drivers from 2024 to Sept 2026, while warning that some employers and vehicle owners are enabling illegal driving.
29-09-2026
Why Is Malaysia's Finance Ministry Testing A GWM WEY G9? Here's What We Know
Malaysia's Finance Ministry is evaluating a locally assembled GWM WEY G9 PHEV with SPANCO. Here's what the government fleet trial actually means.
25-09-2026
Several Riders Skidded At The Same 'Anti-Skid' Lane. Here's What JKR Says
Several riders skidded on an 'anti-skid' Federal Highway motorcycle lane. JKR is investigating the surface, contamination and other possible factors.
25-09-2026
Only RM10K Separates The Two CKD iCAUR 03s - Here's What You Get
Both iCAUR 03 variants are now CKD in Malaysia. With just RM10,140 between the RWD and iWD, here's what the extra money gets you.
25-09-2026
JPJ Letting Rohingya Apply For Driving Licences? Here's The Fact Check
A viral post claims JPJ is proposing to let Rohingya apply for driving licences in Malaysia. JPJ says the claim is false and has reported it to MCMC.
24-09-2026
Going To Singapore From Oct 6? Check Your VEP Or Risk Getting Turned Back
Driving to Singapore from Oct 6? Foreign vehicles will face VEP checks during SG Arrival Card submission. Here's what Malaysian drivers need to know.
24-09-2026
Show More
trending_flat