Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana Malaysia Bhd has postponed the opening of the Shah Alam LRT Line, emphasising that passenger safety must come first and avoiding any repeat of the 2021 Kelana Jaya LRT collision that injured over 200 passengers.
According to Wan Agyl Wan Hassan, founder and CEO of MY Mobility Vision, the construction work on the line is nearly complete, but the technology running the trains is far more complex.

"The Shah Alam LRT is fully automated (GoA4), meaning the system controls speed, braking, doors, and train spacing entirely via software. Even a minor glitch could cause a train to brake suddenly or disrupt schedules
“Each train must complete a fault-free run (FFR) as required by the Land Public Transport Agency (APAD)
“If a problem occurs, testing must start over. It may not be popular, but it’s necessary to make sure passengers are truly safe," he told The Star.
He added that many countries, including Singapore, the UK, and Australia, have delayed the launch of automated rail lines at the last minute to deal with software integration issues.
-full_normal-(1).jpg)
“In modern rail systems, postponing safety is normal. What’s unusual is opening a system that isn’t fully stable,” Wan Agyl added.
Samirul Ariff Othman, senior consultant at Global Asia Consulting, said extending the testing period is a principled decision, not an unnecessary delay.
“It prioritises system reliability and passenger safety. Rushing the launch could lead to trains stopping mid-track, brake failures, repeated delays, and a damaged public image

"Addressing all issues before operations start prevents costly repairs and long-term negative perception," he noted in the same report.
Source: The star.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRS2271
SELANGOR
BSU1401
JOHOR
JF384J
PULAU PINANG
PSF9490
PERAK
APL8039
PAHANG
CFH8716
KEDAH
KGJ3035
NEGERI SEMBILAN
NEM1410
KOTA KINABALU
SJU3520
KUCHING
QAB6589P
Last updated 30 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Forget Luxury Condos! PM Anwar Wants Affordable Homes Next To Train Stations – Here’s The Plan
PM Anwar wants affordable homes, not luxury condos, next to LRT3 stations! See the 4 locations identified for new Transit-Oriented Developments in the Klang Valley.
30-06-2026
LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays
The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.
24-02-2026
LRT3 Shah Alam Line Expected To Open In June
After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.
05-02-2026
Prasarana Ridership Jumps 11% in 2025
Prasarana ridership jumps 11% in 2025 hitting 1.31 million users.
07-01-2026
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
LRT3 Might Be Delayed Again As Testing Encounters Issues - Report
The LRT3, expected to open early next year, may face further delays due to ongoing signalling system issues.
07-12-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
LRT3 Will Begin Operations On Sept 30 - Loke
LRT3 will begin operating on September 30 this year, Transport Minister Anthony Loke announced.
27-02-2025
Latest News
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
Malaysia's First Locally Built EV And PHEV Pick-Ups Are Coming From JAC
JAC will locally assemble its T9 EV and PHEV in Kulim, creating Malaysia's first CKD electrified pick-ups, with exports also being explored.
29-09-2026
Nearly Half A Million Summonses To Foreign Drivers: JPJ Says Some Employers Are Enabling It
JPJ issued 481,119 summonses to foreign drivers from 2024 to Sept 2026, while warning that some employers and vehicle owners are enabling illegal driving.
29-09-2026
Why Is Malaysia's Finance Ministry Testing A GWM WEY G9? Here's What We Know
Malaysia's Finance Ministry is evaluating a locally assembled GWM WEY G9 PHEV with SPANCO. Here's what the government fleet trial actually means.
25-09-2026
Several Riders Skidded At The Same 'Anti-Skid' Lane. Here's What JKR Says
Several riders skidded on an 'anti-skid' Federal Highway motorcycle lane. JKR is investigating the surface, contamination and other possible factors.
25-09-2026
Only RM10K Separates The Two CKD iCAUR 03s - Here's What You Get
Both iCAUR 03 variants are now CKD in Malaysia. With just RM10,140 between the RWD and iWD, here's what the extra money gets you.
25-09-2026
JPJ Letting Rohingya Apply For Driving Licences? Here's The Fact Check
A viral post claims JPJ is proposing to let Rohingya apply for driving licences in Malaysia. JPJ says the claim is false and has reported it to MCMC.
24-09-2026
Going To Singapore From Oct 6? Check Your VEP Or Risk Getting Turned Back
Driving to Singapore from Oct 6? Foreign vehicles will face VEP checks during SG Arrival Card submission. Here's what Malaysian drivers need to know.
24-09-2026
Show More
trending_flat
