LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing

Kumeran Sagathevan

Share via

LRT3-ShahAlam-Line-(1)-full_normal.jpg


Although solutions have been developed for all 33 technical issues flagged on the LRT3 Shah Alam Line, the systems have yet to complete full testing to confirm they perform reliably under operating conditions.

According to Sinar Harian, Shah Alam Line COO Mohd Ariffin Idris said the project team is now focused on extended and continuous testing, aimed at validating whether the fixes introduced truly resolve the problems encountered earlier.


482007087_633007019374783_2319286765909882135_n.jpg

He explained that while corrective measures are already in place, they must be proven through rigorous trials before the line can be considered operationally ready. Testing, he said, is still ongoing and remains a critical phase of the project.

A major area of attention is the system software, which is being upgraded to the latest baseline to ensure it can cope with both existing faults and any new issues that may emerge during testing.

Mohd Ariffin added that failure-free run (FFR) testing is currently being carried out on all trains assigned to the Shah Alam Line. A total of 22 trains must undergo the process, with each test monitored by the Land Public Transport Agency (APAD) as part of standard regulatory requirements.


481670118_633007029374782_6626559310987309250_n.jpg


Even trains that have already clocked the required mileage are not exempt, as they still need to be reassessed to ensure every technical and safety criterion is fully satisfied.

According to him, the line cannot open to passengers until all trains pass FFR testing and the entire system, including infrastructure and signalling, is confirmed to be fully complete and stable.

Testing is conducted around the clock, including overnight sessions, with specialists from original equipment manufacturers involved to address specific technical challenges. These include signalling systems supplied from Germany and rolling stock sourced from China.

He noted that uncovering new issues during dry runs is not unusual, and any problems identified will be rectified before further testing continues to ensure long-term stability.


PANEL-A-Quick-Facts-2.png


As for the start of public operations, Mohd Ariffin said an official projection is expected to be announced by senior management around January next year, once testing reaches a more conclusive stage.

Earlier reports by Prasarana Malaysia Bhd revealed that the 33 technical issues, largely linked to software errors and system disruptions, were identified during two and a half months of testing and were a key reason behind delays to the line’s launch.

Among the problems detected were trains failing to stop precisely at platforms, issues with door operations, incorrect speed settings, failures in automatic train movement, and unintended train movement when the system should have remained static.


Share This Article

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

JPJ Running Numbers

KUALA LUMPUR

VRS2271

SELANGOR

BSU1401

JOHOR

JF384J

PULAU PINANG

PSF9490

PERAK

APL8039

PAHANG

CFH8716

KEDAH

KGJ3035

NEGERI SEMBILAN

NEM1410

KOTA KINABALU

SJU3520

KUCHING

QAB6589P

Last updated 30 Sep, 2026

Fuel Price

Petrol

RON 95

RM 3.97

+1.38

RON 97

RM 4.90

+1.75

RON 100

RM 7.20

+2.20

VPR

RM 8.23

+2.00

Diesel

EURO 5 B10

RM 5.12

+2.08

EURO 5 B7

RM 5.32

+2.08

Last updated 30 Apr, 2026

Related News

Auto News

Save RM6,000 A Year? We Calculated Your Real Savings By Switching To The New LRT3

LRT3 Shah Alam Line is now open with free rides until July 31. See how switching to public transport can save you RM6,000 annually in fuel, tolls, and parking.

29-06-2026
Auto News

From 80 Sen To RM4.30: A Simple Breakdown Of The New LRT3 Fares

Planning to ride the new LRT3? Get a simple breakdown of the Shah Alam Line fares.

25-06-2026
Auto News

It’s Happening! After Years Of Delays, The LRT3 Is Finally Ready To Start Operations

The long-awaited LRT3 Shah Alam Line is officially set to begin operations by the end of this month, as confirmed by Transport Minister Anthony Loke.

18-06-2026
Auto News

Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far

The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.

05-03-2026
Auto News

LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays

The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.

24-02-2026
Auto News

LRT3 Shah Alam Line Expected To Open In June

After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.

05-02-2026
Auto News

Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash

Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.

15-12-2025
Auto News

LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set

The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.

12-12-2025

Latest News

Auto News

Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds

The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.

29-09-2026
Auto News

Malaysia's First Locally Built EV And PHEV Pick-Ups Are Coming From JAC

JAC will locally assemble its T9 EV and PHEV in Kulim, creating Malaysia's first CKD electrified pick-ups, with exports also being explored.

29-09-2026
Auto News

Nearly Half A Million Summonses To Foreign Drivers: JPJ Says Some Employers Are Enabling It

JPJ issued 481,119 summonses to foreign drivers from 2024 to Sept 2026, while warning that some employers and vehicle owners are enabling illegal driving.

29-09-2026
Auto News

Why Is Malaysia's Finance Ministry Testing A GWM WEY G9? Here's What We Know

Malaysia's Finance Ministry is evaluating a locally assembled GWM WEY G9 PHEV with SPANCO. Here's what the government fleet trial actually means.

25-09-2026
Auto News

Several Riders Skidded At The Same 'Anti-Skid' Lane. Here's What JKR Says

Several riders skidded on an 'anti-skid' Federal Highway motorcycle lane. JKR is investigating the surface, contamination and other possible factors.

25-09-2026
Auto News

Only RM10K Separates The Two CKD iCAUR 03s - Here's What You Get

Both iCAUR 03 variants are now CKD in Malaysia. With just RM10,140 between the RWD and iWD, here's what the extra money gets you.

25-09-2026
Auto News

JPJ Letting Rohingya Apply For Driving Licences? Here's The Fact Check

A viral post claims JPJ is proposing to let Rohingya apply for driving licences in Malaysia. JPJ says the claim is false and has reported it to MCMC.

24-09-2026
Auto News

Going To Singapore From Oct 6? Check Your VEP Or Risk Getting Turned Back

Driving to Singapore from Oct 6? Foreign vehicles will face VEP checks during SG Arrival Card submission. Here's what Malaysian drivers need to know.

24-09-2026

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2026 CariCarz.com. All Rights Reserved.