Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

Prime Minister Datuk Seri Anwar Ibrahim calls for the expedited completion of the Pan Borneo Highway project in Sabah, emphasising the importance of avoiding further delays. He has delegated responsibility to the state government to ensure the project, which benefits the people of Sabah, is completed as quickly as possible.
"Pan Borneo Highway in Sarawak is nearly finished, but Sabah's section is still lagging. We've agreed with the Sabah state government to expedite it," Anwar stated.
He also mentioned that the task of overseeing this matter has been entrusted to Works Minister Datuk Seri Alexander Nanta Linggi and Deputy Prime Minister Datuk Seri Fadillah Yusof, stressing his desire for rapid progress so that the people of Sabah can benefit from this multi-billion-ringgit project, the longest highway in Malaysia.
-full_normal.webp)
Unlike toll highways in Peninsular Malaysia, the Pan Borneo Highway in Sabah and Sarawak is toll-free, provided by the government for the public. As of July 29, Nanta reported that Phase 1A of the Pan Borneo Highway in Sabah was 77.41% complete, with full completion expected by 2026. As of now 11 of the 15 work packages have not yet been finished, with four already finished.
Anwar said that, in regards to project delays, he would not take any justifications from any of the parties concerned. He reported on continuing conversations amongst different governmental levels about current problems such as acute poverty, water, flooding, electricity, and infrastructure.
Anwar also added that although problems like potholes that prevent pupils from going to school and improvised suspension bridges made of thin planks were passed down from the previous government, it is the responsibility of the current administration to address them rather than making excuses.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRS2271
SELANGOR
BSU1401
JOHOR
JF384J
PULAU PINANG
PSF9490
PERAK
APL8039
PAHANG
CFH8716
KEDAH
KGJ3035
NEGERI SEMBILAN
NEM1410
KOTA KINABALU
SJU3520
KUCHING
QAB6589P
Last updated 30 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway
The construction of Phase 1A of the LPB is taking longer than anticipated due to difficult land acquisition and utility relocation process.
07-10-2024
Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target
Sabah Pan Borneo Highway in final open tender review for 15 of the 19 work packages for Phase 1B of the project.
26-06-2024
Pan Borneo highway status in Sabah and Sarawak
The condition of the Pan Borneo Highway in Sabah and Sarawak
06-12-2022
Trans Borneo Highway’s Miri Stretch Set To Begin Construction Next Year
Work on the 4.95km Miri Section will move from planning to physical construction in the first quarter of 2026.
04-12-2025
Trans Borneo Highway’s Miri Stretch Set To Begin Construction Next Year
Work on the 4.95km Miri Section will move from planning to physical construction in the first quarter of 2026.
04-12-2025
Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway
The construction of Phase 1A of the LPB is taking longer than anticipated due to difficult land acquisition and utility relocation process.
07-10-2024
Pan Borneo Highway Project Will Be Completed This Year - Nanta
98.91% of the work on the Sarawak Pan Borneo Highway (LPB) project had been completed, says the works minister.
13-02-2024
PMX: Perodua EV Launch Confirmed This Month, Set to Be “National Agenda”
PMX confirms Perodua’s first EV will launch by month-end, and will be elevated to a “national agenda”.
11-11-2025
Latest News
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
Malaysia's First Locally Built EV And PHEV Pick-Ups Are Coming From JAC
JAC will locally assemble its T9 EV and PHEV in Kulim, creating Malaysia's first CKD electrified pick-ups, with exports also being explored.
29-09-2026
Nearly Half A Million Summonses To Foreign Drivers: JPJ Says Some Employers Are Enabling It
JPJ issued 481,119 summonses to foreign drivers from 2024 to Sept 2026, while warning that some employers and vehicle owners are enabling illegal driving.
29-09-2026
Why Is Malaysia's Finance Ministry Testing A GWM WEY G9? Here's What We Know
Malaysia's Finance Ministry is evaluating a locally assembled GWM WEY G9 PHEV with SPANCO. Here's what the government fleet trial actually means.
25-09-2026
Several Riders Skidded At The Same 'Anti-Skid' Lane. Here's What JKR Says
Several riders skidded on an 'anti-skid' Federal Highway motorcycle lane. JKR is investigating the surface, contamination and other possible factors.
25-09-2026
Only RM10K Separates The Two CKD iCAUR 03s - Here's What You Get
Both iCAUR 03 variants are now CKD in Malaysia. With just RM10,140 between the RWD and iWD, here's what the extra money gets you.
25-09-2026
JPJ Letting Rohingya Apply For Driving Licences? Here's The Fact Check
A viral post claims JPJ is proposing to let Rohingya apply for driving licences in Malaysia. JPJ says the claim is false and has reported it to MCMC.
24-09-2026
Going To Singapore From Oct 6? Check Your VEP Or Risk Getting Turned Back
Driving to Singapore from Oct 6? Foreign vehicles will face VEP checks during SG Arrival Card submission. Here's what Malaysian drivers need to know.
24-09-2026
Show More
trending_flat