Trans Borneo Highway’s Miri Stretch Set To Begin Construction Next Year
Construction on the Miri stretch of the Trans Borneo Highway is finally moving forward, with the Works Ministry confirming that physical work is expected to begin in the first quarter of 2026.
Works Minister Datuk Seri Alexander Nanta Linggi told the Dewan Negara that the 4.951-kilometre section, formerly known as Miri Work Package 12 under Phase 2 of the Pan Borneo Highway (LPB2), is still in its pre-construction stage while the federal government completes the procurement and tender process.
"LPB2 has now been rebranded as two separate projects which are the Trans Borneo Highway (LTB) and the Northern Coastal Highway (NCH)," he explained.
This came in response to Senator Datuk Ahmad Ibrahim, who asked for updates on Sarawak’s LPB2 progress and how the ministry plans to avoid delays caused by contractor issues or the need for extra funding.

According to Nanta, Work Package 13 (Limbang) and Work Package 14 (Lawas) now fall under the NCH project and are being implemented by RECODA under the supervision of the Sarawak government.
As for the Pan Borneo Highway in Sarawak, Nanta reported that the 786-kilometre route has reached 99.98% progress as of Oct.
"Ten out of eleven work packages are already completed and opened in stages to the public. The last remaining package, WPC 11, however, cannot meet its original 2025 completion timeline," Nanta added.
He said the delay stems from the urgent need to replace old water pipes belonging to Sarawak Water Sdn Bhd along the affected 4.2-kilometre stretch. The pipe replacement must be done first to prevent supply disruptions in Miri and avoid future road damage.

The Works Ministry, along with Sarawak JKR, contractors and relevant agencies, is currently renegotiating costs and scope. Pipe diversion and road upgrades are expected to roll out in phases from early 2026, with full completion targeted for the first quarter of 2029.
"Finishing WPC 11 will mark the full completion of the Pan Borneo Highway in Sarawak
"Continuous monitoring is in place to keep the projects on track and prevent delays due to contractor or funding issues," the minister assured.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VSA4819
SELANGOR
BSV2920
JOHOR
JH7613J
PULAU PINANG
PSH5424
PERAK
APN2134
PAHANG
CFJ4636
KEDAH
KGJ9130
NEGERI SEMBILAN
NEM6571
KOTA KINABALU
SJV2938
KUCHING
QAB704Q
Last updated 23 Nov, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah
PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.
06-08-2024
Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway
The construction of Phase 1A of the LPB is taking longer than anticipated due to difficult land acquisition and utility relocation process.
07-10-2024
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah
PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.
06-08-2024
Pan Borneo Highway Project Will Be Completed This Year - Nanta
98.91% of the work on the Sarawak Pan Borneo Highway (LPB) project had been completed, says the works minister.
13-02-2024
Works Ministry Denies Removing Barriers at Fatal Terengganu Crash Site
Works minister has refuted claims that his ministry removed the safety signs and concrete barriers at the fatal Terengganu crash site.
08-12-2025
Works Ministry Yet To Receive Genting Road Charge Proposal
Works Ministry clarifies no formal proposal received as Genting Malaysia plans charges for road maintenance.
19-11-2025
Genting Toll: State Leaders Seek Resident-Friendly Approach
Pahang and Bentong representatives call for reasonable rates and safeguards as Genting prepares to introduce its toll fee.
17-11-2025
Nanta: Barrier-Free ANPR Toll System Still at RFP Stage
The Works Ministry is inviting proposals for an ANPR-based barrier-free MLFF toll system.
10-11-2025
Latest News
Women Want Female E-Hailing Drivers. But Are There Enough Options In Malaysia?
Looking for female e-hailing drivers in Malaysia? Explore women-only rides, service availability, passenger safety and legal transport requirements.
18-11-2026
Malaysia Toll Abolition Explained: RM400 Billion And Highway Concessions
Why could abolishing Malaysia's highway tolls cost RM400 billion? Explore highway concessions, toll payments and alternatives to nationwide toll abolition.
17-11-2026
GWM Malaysia 2026 Year-End Deals: Prices, Warranties And Financing Offers
GWM Malaysia's 2026 year-end deals include the ORA Good Cat from RM94,000, Haval H6 HEV privileges, WEY G9 financing and Tank SUV warranties.
16-11-2026
Honda Sumber Auto Edaran PJ Closes After 25 Years Of Operations
Honda Sumber Auto Edaran PJ has closed after 25 years, with over 27,000 cars sold. Here's what existing Honda customers should know.
16-11-2026
All-New Nissan X-Trail e-POWER x e-4ORCE Makes First Public Appearance In Malaysia
The new Nissan X-Trail e-POWER x e-4ORCE makes its first public road appearance in KL ahead of its Q4 2026 Malaysia launch. Here's what we know.
16-11-2026
Proton Sales 2026: Geely-Based Models Overtake Homegrown Cars
Geely-based Protons lead homegrown models in 2026 registrations. But the e.MAS lineup and Saga sales reveal a more interesting story.
13-11-2026
Johor Highway Upgrades: PLUS And Senai-Desaru May Open Early
Two Johor highway stretches on PLUS and Senai-Desaru may open early in 2027. Here's where they are, proposed dates and what drivers should know.
13-11-2026
Loke Says Some Welcomed His Resignation, Urges JPJ To Maintain Enforcement
Anthony Loke says some cheered his resignation, expecting JPJ's overloaded lorry crackdown to ease. Will enforcement continue without him?
12-11-2026
Show More
trending_flat
Malaysia First Used Car and EV Consignment Platform
This is the best place to sell your car at true market value. Instead of accepting low dealer trade-ins, we handle everything and connect your car directly to genuine buyers for the highest price.

Understanding CariCarzAutomall Consignment Plan


Approved 200-Check Points Inspection

7 Day Money Back Guarantee

One Year Extended Warranty

No Hidden Charge