Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete

Kumeran Sagathevan

Share via

453218537_1007686224479436_6295259034249152090_n.jpg


The Light Rail Transit 3 (LRT3) project is on track to ferry passengers by the third quarter (Q3) of next year (2025), says Transport Minister Anthony Loke.

According to Loke, the physical construction on the LRT3 project is expected to be finished by Oct this year, having progressed to a 95.6% completion rate. Subsequently, there will be a three to four month testing and commissioning phase after system integration, followed by further tests through early next year.


453382648_1007686204479438_2704506612600314558_n.jpg453252451_1007686131146112_7532968729376801684_n.jpg


Set to serve more than two million people, the LRT3 project in Petaling Jaya extends from Klang to Bandar Utama. Even though the Covid-19 epidemic caused delays, Prasarana Malaysia Bhd and its contractors have been working hard to make up for lost time and keep the project on schedule.


453495284_1007686081146117_6793017307642832688_n.jpg


Loke went on to say that the cabinet decided on July 5 to bring back five stations that had been cancelled: Tropicana, Temasya, Raja Muda, Bukit Raja, and Bandar Botanik. However, this would necessitate more work, like building three bus depots, expanding the train station at Johan Setia, as well as acquiring 150 feeder electric buses and seven sets of three-car trains.


453219303_1007686217812770_6307662427527364152_n.jpg


It is anticipated to cost RM3.8 billion to reopen these five stations, which were first put on hold in 2018 owing to low passenger ridership projections. This budget pays for contractors, rolling stock acquisitions, electronic bus construction, bus depot construction, infrastructure, system costs, and the restoration of the project scope.


453083082_1007686077812784_7157571752057684711_n.jpg453183840_1007686161146109_8992891956263002173_n.jpg


Loke promised that LRT3, which will have 20 stops, would not be affected by the extra work needed for these stations when it first opens and goes into service. Two more years will be needed for the installation of these five stations. But this won't have an impact on the LRT3's opening or regular operations," he reaffirmed.

The RM16 billion LRT3 project is expected to boost connectivity and public transport choices for Klang Valley residents. LRT3 is expected to be completed and put into service early in the following year, marking a major turning point in the development of public transit in Malaysia.



Source: NewStraitsTimes & FB Warga Prasarana 

Share This Article

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

JPJ Running Numbers

KUALA LUMPUR

VSA4819

SELANGOR

BSV2920

JOHOR

JH7613J

PULAU PINANG

PSH5424

PERAK

APN2134

PAHANG

CFJ4636

KEDAH

KGJ9130

NEGERI SEMBILAN

NEM6571

KOTA KINABALU

SJV2938

KUCHING

QAB704Q

Last updated 23 Nov, 2026

Fuel Price

Petrol

RON 95

RM 3.97

+1.38

RON 97

RM 4.90

+1.75

RON 100

RM 7.20

+2.20

VPR

RM 8.23

+2.00

Diesel

EURO 5 B10

RM 5.12

+2.08

EURO 5 B7

RM 5.32

+2.08

Last updated 30 Apr, 2026

Related News

Auto News

Forget Luxury Condos! PM Anwar Wants Affordable Homes Next To Train Stations – Here’s The Plan

PM Anwar wants affordable homes, not luxury condos, next to LRT3 stations! See the 4 locations identified for new Transit-Oriented Developments in the Klang Valley.

30-06-2026
Auto News

LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays

The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.

24-02-2026
Auto News

LRT3 Shah Alam Line Expected To Open In June

After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.

05-02-2026
Auto News

Prasarana Ridership Jumps 11% in 2025

Prasarana ridership jumps 11% in 2025 hitting 1.31 million users.

Auto News

Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash

Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.

15-12-2025
Auto News

LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set

The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.

12-12-2025
Auto News

LRT3 Might Be Delayed Again As Testing Encounters Issues - Report

The LRT3, expected to open early next year, may face further delays due to ongoing signalling system issues.

07-12-2025
Auto News

Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3

Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.

Latest News

Auto News

Women Want Female E-Hailing Drivers. But Are There Enough Options In Malaysia?

Looking for female e-hailing drivers in Malaysia? Explore women-only rides, service availability, passenger safety and legal transport requirements.

18-11-2026
Auto News

Malaysia Toll Abolition Explained: RM400 Billion And Highway Concessions

Why could abolishing Malaysia's highway tolls cost RM400 billion? Explore highway concessions, toll payments and alternatives to nationwide toll abolition.

17-11-2026
Auto News

GWM Malaysia 2026 Year-End Deals: Prices, Warranties And Financing Offers

GWM Malaysia's 2026 year-end deals include the ORA Good Cat from RM94,000, Haval H6 HEV privileges, WEY G9 financing and Tank SUV warranties.

16-11-2026
Auto News

Honda Sumber Auto Edaran PJ Closes After 25 Years Of Operations

Honda Sumber Auto Edaran PJ has closed after 25 years, with over 27,000 cars sold. Here's what existing Honda customers should know.

16-11-2026
Auto News

All-New Nissan X-Trail e-POWER x e-4ORCE Makes First Public Appearance In Malaysia

The new Nissan X-Trail e-POWER x e-4ORCE makes its first public road appearance in KL ahead of its Q4 2026 Malaysia launch. Here's what we know.

16-11-2026
Auto News

Proton Sales 2026: Geely-Based Models Overtake Homegrown Cars

Geely-based Protons lead homegrown models in 2026 registrations. But the e.MAS lineup and Saga sales reveal a more interesting story.

13-11-2026
Auto News

Johor Highway Upgrades: PLUS And Senai-Desaru May Open Early

Two Johor highway stretches on PLUS and Senai-Desaru may open early in 2027. Here's where they are, proposed dates and what drivers should know.

13-11-2026
Auto News

Loke Says Some Welcomed His Resignation, Urges JPJ To Maintain Enforcement

Anthony Loke says some cheered his resignation, expecting JPJ's overloaded lorry crackdown to ease. Will enforcement continue without him?

12-11-2026

Show More

trending_flat

Malaysia First Used Car and EV Consignment Platform

This is the best place to sell your car at true market value. Instead of accepting low dealer trade-ins, we handle everything and connect your car directly to genuine buyers for the highest price.

I want to consign my car! Trade-in price too low.

CariCarz Automall

Understanding CariCarzAutomall Consignment Plan

Approved 200-Check Points Inspection

7 Day Money Back Guarantee

One Year Extended Warranty

No Hidden Charge

About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2026 CariCarz.com. All Rights Reserved.