"Wait, Why Is It Taking So Long?" — 4 Things Slowing Down The Pan Borneo Highway In Sabah Right Now

Pan Borneo Highway
If you’ve driven between Sandakan and Lahad Datu lately, you’ve probably spent more time looking at orange traffic cones than actual scenery.
The Pan Borneo Highway is the "dream" project we’ve been waiting for, but let’s be real, the progress bar feels like it’s stuck at 99% loading. Recently, Chief Minister Datuk Seri Hajiji Noor went down to the ground to inspect Work Package 25 (WP25), and he didn’t sugarcoat it.
The 14.96km stretch from Kampung Perpaduan Datuk Moh to Sukau is currently at 12.35% physical progress, slightly behind its 15.30% target. So, what’s the hold-up?
Here are the 4 major "speed bumps" keeping the machines from moving faster:
1. The "Invisible" Utility Maze
This is the big one. Hajiji identified utility relocation as the primary factor slowing down earthworks.
Think about it: before you can build a massive highway, you have to move miles of SESB electricity poles, water pipes, and fiber optic cables that have been there for decades. Moving these requires high-level coordination between agencies, and one wrong move could leave a whole village without water or TikTok.
2. The Logistical Tug-of-War
Moving heavy machinery through rural Sabah isn’t like driving a Myvi to the mall. The CM noted that logistical challenges are a major constraint. Getting raw materials, giant bridge beams, and specialized equipment into areas like Sukau requires precise timing and solid ground, both of which are hard to find in a construction zone.
3. "Temporary Access" Nightmares
We’ve all seen them, those narrow, bumpy diversions that keep you at a 20km/h crawl. These temporary access issues within the project area don't just annoy drivers; they actually slow down the workers too. Managing traffic while trying to build a multi-storey flyover on the same spot is basically a high-stakes game of Tetris.
4. Demolition & Land Dramas

Chief Minister of Sabah, Datuk Seri Hajiji Noor.
You can't build a road where a house is standing. Hajiji mentioned that land acquisition and the demolition of existing structures are still ongoing hurdles. Negotiating with land owners and ensuring everyone is compensated fairly takes time, and until the "site clear" signal is given, the bulldozers have to wait.
Is there light at the end of the tunnel?
Despite the delays, there is a "Save the Date" on the calendar. This RM269.9 million project is scheduled for completion by February 2028.
Once done, WP25 will feature:
- A multi-storey interchange (Flyover)
- Bus stops
- Pedestrian bridges
- Upgraded drainage to prevent those "flash flood" surprises
The government is pushing for closer coordination between agencies to stop the "blame game" and get the tarmac moving. For now, keep your snacks ready and your patience high, the road to a better Sabah is still under construction.
What do you think? Is 2028 a realistic goal or just another "Janji Manis"? Let us know in the comments!
Written By
Sofea Najmi
A Bachelor of English Language and Literature graduate with an obsession for the finer details. Sofea uses her background in translation to decode the technicalities of automotive innovation. She is dedicated to delivering impactful, meticulously researched articles that provide a narrative far beyond the spec sheet. LinkedIn: https://bit.ly/3C018vv
JPJ Running Numbers
KUALA LUMPUR
VRS2271
SELANGOR
BSU1401
JOHOR
JF384J
PULAU PINANG
PSF9490
PERAK
APL8039
PAHANG
CFH8716
KEDAH
KGJ3035
NEGERI SEMBILAN
NEM1410
KOTA KINABALU
SJU3520
KUCHING
QAB6589P
Last updated 30 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Latest News
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
Malaysia's First Locally Built EV And PHEV Pick-Ups Are Coming From JAC
JAC will locally assemble its T9 EV and PHEV in Kulim, creating Malaysia's first CKD electrified pick-ups, with exports also being explored.
29-09-2026
Nearly Half A Million Summonses To Foreign Drivers: JPJ Says Some Employers Are Enabling It
JPJ issued 481,119 summonses to foreign drivers from 2024 to Sept 2026, while warning that some employers and vehicle owners are enabling illegal driving.
29-09-2026
Why Is Malaysia's Finance Ministry Testing A GWM WEY G9? Here's What We Know
Malaysia's Finance Ministry is evaluating a locally assembled GWM WEY G9 PHEV with SPANCO. Here's what the government fleet trial actually means.
25-09-2026
Several Riders Skidded At The Same 'Anti-Skid' Lane. Here's What JKR Says
Several riders skidded on an 'anti-skid' Federal Highway motorcycle lane. JKR is investigating the surface, contamination and other possible factors.
25-09-2026
Only RM10K Separates The Two CKD iCAUR 03s - Here's What You Get
Both iCAUR 03 variants are now CKD in Malaysia. With just RM10,140 between the RWD and iWD, here's what the extra money gets you.
25-09-2026
JPJ Letting Rohingya Apply For Driving Licences? Here's The Fact Check
A viral post claims JPJ is proposing to let Rohingya apply for driving licences in Malaysia. JPJ says the claim is false and has reported it to MCMC.
24-09-2026
Going To Singapore From Oct 6? Check Your VEP Or Risk Getting Turned Back
Driving to Singapore from Oct 6? Foreign vehicles will face VEP checks during SG Arrival Card submission. Here's what Malaysian drivers need to know.
24-09-2026
Show More
trending_flat