"Wait, Why Is It Taking So Long?" — 4 Things Slowing Down The Pan Borneo Highway In Sabah Right Now

Pan Borneo Highway
If you’ve driven between Sandakan and Lahad Datu lately, you’ve probably spent more time looking at orange traffic cones than actual scenery.
The Pan Borneo Highway is the "dream" project we’ve been waiting for, but let’s be real, the progress bar feels like it’s stuck at 99% loading. Recently, Chief Minister Datuk Seri Hajiji Noor went down to the ground to inspect Work Package 25 (WP25), and he didn’t sugarcoat it.
The 14.96km stretch from Kampung Perpaduan Datuk Moh to Sukau is currently at 12.35% physical progress, slightly behind its 15.30% target. So, what’s the hold-up?
Here are the 4 major "speed bumps" keeping the machines from moving faster:
1. The "Invisible" Utility Maze
This is the big one. Hajiji identified utility relocation as the primary factor slowing down earthworks.
Think about it: before you can build a massive highway, you have to move miles of SESB electricity poles, water pipes, and fiber optic cables that have been there for decades. Moving these requires high-level coordination between agencies, and one wrong move could leave a whole village without water or TikTok.
2. The Logistical Tug-of-War
Moving heavy machinery through rural Sabah isn’t like driving a Myvi to the mall. The CM noted that logistical challenges are a major constraint. Getting raw materials, giant bridge beams, and specialized equipment into areas like Sukau requires precise timing and solid ground, both of which are hard to find in a construction zone.
3. "Temporary Access" Nightmares
We’ve all seen them, those narrow, bumpy diversions that keep you at a 20km/h crawl. These temporary access issues within the project area don't just annoy drivers; they actually slow down the workers too. Managing traffic while trying to build a multi-storey flyover on the same spot is basically a high-stakes game of Tetris.
4. Demolition & Land Dramas

Chief Minister of Sabah, Datuk Seri Hajiji Noor.
You can't build a road where a house is standing. Hajiji mentioned that land acquisition and the demolition of existing structures are still ongoing hurdles. Negotiating with land owners and ensuring everyone is compensated fairly takes time, and until the "site clear" signal is given, the bulldozers have to wait.
Is there light at the end of the tunnel?
Despite the delays, there is a "Save the Date" on the calendar. This RM269.9 million project is scheduled for completion by February 2028.
Once done, WP25 will feature:
- A multi-storey interchange (Flyover)
- Bus stops
- Pedestrian bridges
- Upgraded drainage to prevent those "flash flood" surprises
The government is pushing for closer coordination between agencies to stop the "blame game" and get the tarmac moving. For now, keep your snacks ready and your patience high, the road to a better Sabah is still under construction.
What do you think? Is 2028 a realistic goal or just another "Janji Manis"? Let us know in the comments!
Written By
Sofea Najmi
A Bachelor of English Language and Literature graduate with an obsession for the finer details. Sofea uses her background in translation to decode the technicalities of automotive innovation. She is dedicated to delivering impactful, meticulously researched articles that provide a narrative far beyond the spec sheet. LinkedIn: https://bit.ly/3C018vv
JPJ Running Numbers
KUALA LUMPUR
VSA4819
SELANGOR
BSV2920
JOHOR
JH7613J
PULAU PINANG
PSH5424
PERAK
APN2134
PAHANG
CFJ4636
KEDAH
KGJ9130
NEGERI SEMBILAN
NEM6571
KOTA KINABALU
SJV2938
KUCHING
QAB704Q
Last updated 23 Nov, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Latest News
Women Want Female E-Hailing Drivers. But Are There Enough Options In Malaysia?
Looking for female e-hailing drivers in Malaysia? Explore women-only rides, service availability, passenger safety and legal transport requirements.
18-11-2026
Malaysia Toll Abolition Explained: RM400 Billion And Highway Concessions
Why could abolishing Malaysia's highway tolls cost RM400 billion? Explore highway concessions, toll payments and alternatives to nationwide toll abolition.
17-11-2026
GWM Malaysia 2026 Year-End Deals: Prices, Warranties And Financing Offers
GWM Malaysia's 2026 year-end deals include the ORA Good Cat from RM94,000, Haval H6 HEV privileges, WEY G9 financing and Tank SUV warranties.
16-11-2026
Honda Sumber Auto Edaran PJ Closes After 25 Years Of Operations
Honda Sumber Auto Edaran PJ has closed after 25 years, with over 27,000 cars sold. Here's what existing Honda customers should know.
16-11-2026
All-New Nissan X-Trail e-POWER x e-4ORCE Makes First Public Appearance In Malaysia
The new Nissan X-Trail e-POWER x e-4ORCE makes its first public road appearance in KL ahead of its Q4 2026 Malaysia launch. Here's what we know.
16-11-2026
Proton Sales 2026: Geely-Based Models Overtake Homegrown Cars
Geely-based Protons lead homegrown models in 2026 registrations. But the e.MAS lineup and Saga sales reveal a more interesting story.
13-11-2026
Johor Highway Upgrades: PLUS And Senai-Desaru May Open Early
Two Johor highway stretches on PLUS and Senai-Desaru may open early in 2027. Here's where they are, proposed dates and what drivers should know.
13-11-2026
Loke Says Some Welcomed His Resignation, Urges JPJ To Maintain Enforcement
Anthony Loke says some cheered his resignation, expecting JPJ's overloaded lorry crackdown to ease. Will enforcement continue without him?
12-11-2026
Show More
trending_flat
Malaysia First Used Car and EV Consignment Platform
This is the best place to sell your car at true market value. Instead of accepting low dealer trade-ins, we handle everything and connect your car directly to genuine buyers for the highest price.

Understanding CariCarzAutomall Consignment Plan


Approved 200-Check Points Inspection

7 Day Money Back Guarantee

One Year Extended Warranty

No Hidden Charge