Shah Alam LRT Delayed Again, December Now In Sight
Commuters hoping to ride the new Shah Alam LRT will need to wait a little longer. The 37km line, once scheduled to open on September 30, is now aiming for a December launch, The Star reported.
The delay centres on the project’s toughest hurdle, known as the fault-free run.
Each train must clock thousands of kilometres without breaking down before the line can open to the public. If even one significant fault appears, the entire mileage resets to zero, forcing the test to start all over again.
In a memo to staff, Prasarana Malaysia’s new president and CEO Amir Hamdan called for patience and even prayers. 
Photo: The Star. “God willing, the project will enter the fault-free run on August 25. We pray this test goes smoothly with no more delays so that we can complete the project in time for launch,” he wrote in a note titled 'Call to Prayer', which was sighted by The Star.
The first train must successfully complete 4,000 kilometres of testing, while the remaining sets must each log at least 2,000 kilometres.
The trains also need to run the full stretch from Johan Setia in Klang to Bandar Utama in under an hour, with departures every six minutes, in order to move more than 18,000 passengers an hour in each direction. The delay contrasts with recent assurances.
Transport Minister Anthony Loke told Parliament in late July that the project was 99% complete. Yet, days earlier, Prasarana had already hinted that testing would continue until October, suggesting September was always a stretch. .png)
For now, commuters are left waiting once again. The line is almost complete, but the final test will decide if Klang Valley gets a smoother ride by the end of the year.
Source: The Star.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRS2271
SELANGOR
BSU1401
JOHOR
JF384J
PULAU PINANG
PSF9490
PERAK
APL8039
PAHANG
CFH8716
KEDAH
KGJ3035
NEGERI SEMBILAN
NEM1410
KOTA KINABALU
SJU3520
KUCHING
QAB6589P
Last updated 30 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing
All 33 technical problems identified on the Shah Alam Line have proposed fixes, but full testing is still underway.
31-12-2025
LRT3 Enters Final Testing Phase, Govt Targets Dec 31 Opening
LRT3 line is now in its final round of safety and reliability tests, with its launch date hinging on Dec results.
18-11-2025
LRT 3 Will Cost RM9.7 Billion Less Despite 5 Key Station Reinstatement
LRT 3 will cost RM9.72 Billion less even with the reinstatement of five key stations compared to initial 2015 cost quoted.
29-10-2024
Save RM6,000 A Year? We Calculated Your Real Savings By Switching To The New LRT3
LRT3 Shah Alam Line is now open with free rides until July 31. See how switching to public transport can save you RM6,000 annually in fuel, tolls, and parking.
29-06-2026
From 80 Sen To RM4.30: A Simple Breakdown Of The New LRT3 Fares
Planning to ride the new LRT3? Get a simple breakdown of the Shah Alam Line fares.
25-06-2026
It’s Happening! After Years Of Delays, The LRT3 Is Finally Ready To Start Operations
The long-awaited LRT3 Shah Alam Line is officially set to begin operations by the end of this month, as confirmed by Transport Minister Anthony Loke.
18-06-2026
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays
The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.
24-02-2026
Latest News
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
Malaysia's First Locally Built EV And PHEV Pick-Ups Are Coming From JAC
JAC will locally assemble its T9 EV and PHEV in Kulim, creating Malaysia's first CKD electrified pick-ups, with exports also being explored.
29-09-2026
Nearly Half A Million Summonses To Foreign Drivers: JPJ Says Some Employers Are Enabling It
JPJ issued 481,119 summonses to foreign drivers from 2024 to Sept 2026, while warning that some employers and vehicle owners are enabling illegal driving.
29-09-2026
Why Is Malaysia's Finance Ministry Testing A GWM WEY G9? Here's What We Know
Malaysia's Finance Ministry is evaluating a locally assembled GWM WEY G9 PHEV with SPANCO. Here's what the government fleet trial actually means.
25-09-2026
Several Riders Skidded At The Same 'Anti-Skid' Lane. Here's What JKR Says
Several riders skidded on an 'anti-skid' Federal Highway motorcycle lane. JKR is investigating the surface, contamination and other possible factors.
25-09-2026
Only RM10K Separates The Two CKD iCAUR 03s - Here's What You Get
Both iCAUR 03 variants are now CKD in Malaysia. With just RM10,140 between the RWD and iWD, here's what the extra money gets you.
25-09-2026
JPJ Letting Rohingya Apply For Driving Licences? Here's The Fact Check
A viral post claims JPJ is proposing to let Rohingya apply for driving licences in Malaysia. JPJ says the claim is false and has reported it to MCMC.
24-09-2026
Going To Singapore From Oct 6? Check Your VEP Or Risk Getting Turned Back
Driving to Singapore from Oct 6? Foreign vehicles will face VEP checks during SG Arrival Card submission. Here's what Malaysian drivers need to know.
24-09-2026
Show More
trending_flat