R&M, Govt in Final Talks to Revive Stalled MEX II Highway
-full_normal.jpg)
The stalled MEX II Highway project has taken a step forward as discussions near completion between the government, sukuk holders, and the Receivers and Managers (R&M) appointed to take over from the original concessionaire.
Works Minister Datuk Seri Alexander Nanta Linggi said the talks are aimed at determining the most viable path to finishing the 18KM highway, which has remained incomplete since 2019.
-full_normal.jpg)
The negotiations, which follow a notice of default issued to the concessionaire in Jan 2022, cover updated completion costs, cash flow projections, traffic studies, toll rates and other measures to ensure the project remains financially and technically sound.
The MEX II project, fully funded under a Build-Operate-Transfer (BOT) model, has no direct government financing, with all obligations now managed by the R&M on behalf of sukuk holders.
Nanta stressed that all progress claims are vetted by the concessionaire, supervising consultant and independent consulting engineer before being submitted to the sukuk holders.
-full_normal.jpg)
-full_normal.jpg)
He also clarified that any alleged false claims, including the RM416 million figure raised by Jerantut MP Khairil Nizam Khirudin fall outside the Works Ministry’s purview, as the project is privately financed.
Originally intended to ease congestion on the existing MEX Expressway, the MEX II extension was slated for completion in Dec 2019. Cash flow problems stalled the works, and the project later drew public attention amid investigations into hundreds of millions of ringgit in suspected false claims.
With talks now in their final stages, a revised plan will be presented to the Cabinet, offering the clearest sign yet that the long-delayed highway may finally reach the finish line.
Source: NST
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRS2271
SELANGOR
BSU1401
JOHOR
JF384J
PULAU PINANG
PSF9490
PERAK
APL8039
PAHANG
CFH8716
KEDAH
KGJ3035
NEGERI SEMBILAN
NEM1410
KOTA KINABALU
SJU3520
KUCHING
QAB6589P
Last updated 30 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
MEX II Putrajaya-KLIA Extension Could Cost RM449 Million – Nanta
Works Minister Dato Sri Alexander Nanta Linggi said the MEX II extension project could cost as much as RM449 million.
03-12-2025
Govt Moves to Revive Delayed MEX II Project
From missed deadlines to MACC probes, troubled MEX II project finally see a turning point as govt swoops in to revive it.
13-05-2025
MACC: RM32 Million Seized From ‘Tan Sri’ Over Expressway Scandal
MACC seizes RM32 Million in luxury assets from a highway concessionaire amid a probe into the misuse of sukuk funds.
30-05-2025
Govt Moves to Revive Delayed MEX II Project
From missed deadlines to MACC probes, troubled MEX II project finally see a turning point as govt swoops in to revive it.
13-05-2025
MEX Highway To Test Out Contra-flow Route Starting 16 November From KM 11.5 to KM 7.9 North Bound
Contra-flow route on a trial basis on the MEX Highway heading north from Putrajaya towards Kuala Lumpur (KM 11.5 - KM 7.9) starting this November 16
13-11-2022
Over 95% of MyJalan Complaints Fixed, Highway Projects Enter Digital Era
KKR says nearly all road damage reports via the MyJalan app have been addressed, LLM rolling out Building Information Modelling.
20-08-2025
KKR Will Accelerate Melaka Road Works Ahead of 2025 ASEAN Chairman’s Meeting
64 locations identified in Melaka by KKR for road repairs ahead of 2025 ASEAN Chairman's meeting and Visit Melaka Year 2024.
23-08-2024
Smart Lane Not Implemented on KLK Due to Hilly Conditions – KKR
Works Minister says that Smart Lanes cannot be implemented on the KL-Karak highway due to its hilly conditions.
30-07-2024
Latest News
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
Malaysia's First Locally Built EV And PHEV Pick-Ups Are Coming From JAC
JAC will locally assemble its T9 EV and PHEV in Kulim, creating Malaysia's first CKD electrified pick-ups, with exports also being explored.
29-09-2026
Nearly Half A Million Summonses To Foreign Drivers: JPJ Says Some Employers Are Enabling It
JPJ issued 481,119 summonses to foreign drivers from 2024 to Sept 2026, while warning that some employers and vehicle owners are enabling illegal driving.
29-09-2026
Why Is Malaysia's Finance Ministry Testing A GWM WEY G9? Here's What We Know
Malaysia's Finance Ministry is evaluating a locally assembled GWM WEY G9 PHEV with SPANCO. Here's what the government fleet trial actually means.
25-09-2026
Several Riders Skidded At The Same 'Anti-Skid' Lane. Here's What JKR Says
Several riders skidded on an 'anti-skid' Federal Highway motorcycle lane. JKR is investigating the surface, contamination and other possible factors.
25-09-2026
Only RM10K Separates The Two CKD iCAUR 03s - Here's What You Get
Both iCAUR 03 variants are now CKD in Malaysia. With just RM10,140 between the RWD and iWD, here's what the extra money gets you.
25-09-2026
JPJ Letting Rohingya Apply For Driving Licences? Here's The Fact Check
A viral post claims JPJ is proposing to let Rohingya apply for driving licences in Malaysia. JPJ says the claim is false and has reported it to MCMC.
24-09-2026
Going To Singapore From Oct 6? Check Your VEP Or Risk Getting Turned Back
Driving to Singapore from Oct 6? Foreign vehicles will face VEP checks during SG Arrival Card submission. Here's what Malaysian drivers need to know.
24-09-2026
Show More
trending_flat