Gamuda Gets Nod To Begin Work On Penang LRT
The Mutiara Line LRT project is now officially in motion, entering its construction phase after receiving the Notice to Proceed (NTP), awarded to Gamuda Bhd on Tuesday.
MRT Corp CEO Datuk Mohd Zarif Hashim told NST that the green light was given after all contract conditions were met.
“We’ve already begun early groundwork ahead of the NTP to make sure everything moves smoothly into the next phase. This includes soil tests, pile checks, environmental monitoring, and site surveys," he says in the NST report. The project’s first phase has been awarded to the SRS Consortium, led by Gamuda (60%), with Loh Phoy Yen Holdings and Ideal Property Development each holding 20%.
-full_normal.jpg)
Early works like utility relocation, piling, and site prep are set to begin next month, with full-scale civil construction expected to start in Q4 2026.
“Projects like this typically follow an S-curve. It's not a sudden jump. Progress starts slow, and we expect the real upward momentum to show after 2027 or 2028,” he explained.
The Mutiara Line broke ground on January 10, launched by Prime Minister Datuk Seri Anwar Ibrahim, marking a major push to modernise Penang’s public transport.
Econpile (M) Sdn Bhd has also secured a RM42.82 million contract from Irama Duta Sdn Bhd for bored piling and related works. 
The 29.5km line will feature 21 stations, linking Penang Silicon Island to Komtar and Penang Sentral, aiming to reduce congestion and boost connectivity between the island and the mainland.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRS2271
SELANGOR
BSU1401
JOHOR
JF384J
PULAU PINANG
PSF9490
PERAK
APL8039
PAHANG
CFH8716
KEDAH
KGJ3035
NEGERI SEMBILAN
NEM1410
KOTA KINABALU
SJU3520
KUCHING
QAB6589P
Last updated 30 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Penang Police Strengthen Security For Mutiara LRT Project
Penang police are coordinating with agencies to ensure the Mutiara LRT project proceeds safely without compromising public security.
18-11-2025
Penang Traffic Woes Persist Despite PTMP - Penang Gerakan
Penang Gerakan urges an independent review of the PTMP, saying poor planning has worsened traffic instead of easing it.
29-09-2025
MRT Corp Justifies RM16.8b Penang LRT Budget
MRT Corp says the RM16.8 billion ceiling for Penang LRT reflects market realities, but MCA wants clearer answers on taxpayers’ money.
21-08-2025
Penang Still Waiting For Green Light From MOT For LRT project
Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.
02-07-2025
Penang Bus Ridership Now Exceeds 46,000 Daily
Penang bus average daily ridership has reached 46,333 after the introduction of on-demand van service and free bus travel.
22-05-2025
Penang LRT Project Progressing Steadily - MRT Corp
Construction of the Mutiara Line Penang LRT project is on track, according to MRT Corp.
21-04-2025
Penang LRT: Nine “Park and Ride” Facilities With 1,100 Parking Space
Penang LRT line to offer 1,100 parking spaces at nine "Park and Ride” Facilities.
27-11-2024
Penang Confirms LRT Work Construction To Begin In December
December will see the start of work on Penang's LRT project, with Lebuh Macallum serving as the location of the first station.
09-10-2024
Latest News
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
Malaysia's First Locally Built EV And PHEV Pick-Ups Are Coming From JAC
JAC will locally assemble its T9 EV and PHEV in Kulim, creating Malaysia's first CKD electrified pick-ups, with exports also being explored.
29-09-2026
Nearly Half A Million Summonses To Foreign Drivers: JPJ Says Some Employers Are Enabling It
JPJ issued 481,119 summonses to foreign drivers from 2024 to Sept 2026, while warning that some employers and vehicle owners are enabling illegal driving.
29-09-2026
Why Is Malaysia's Finance Ministry Testing A GWM WEY G9? Here's What We Know
Malaysia's Finance Ministry is evaluating a locally assembled GWM WEY G9 PHEV with SPANCO. Here's what the government fleet trial actually means.
25-09-2026
Several Riders Skidded At The Same 'Anti-Skid' Lane. Here's What JKR Says
Several riders skidded on an 'anti-skid' Federal Highway motorcycle lane. JKR is investigating the surface, contamination and other possible factors.
25-09-2026
Only RM10K Separates The Two CKD iCAUR 03s - Here's What You Get
Both iCAUR 03 variants are now CKD in Malaysia. With just RM10,140 between the RWD and iWD, here's what the extra money gets you.
25-09-2026
JPJ Letting Rohingya Apply For Driving Licences? Here's The Fact Check
A viral post claims JPJ is proposing to let Rohingya apply for driving licences in Malaysia. JPJ says the claim is false and has reported it to MCMC.
24-09-2026
Going To Singapore From Oct 6? Check Your VEP Or Risk Getting Turned Back
Driving to Singapore from Oct 6? Foreign vehicles will face VEP checks during SG Arrival Card submission. Here's what Malaysian drivers need to know.
24-09-2026
Show More
trending_flat