Penang LRT Project Progressing Steadily - MRT Corp
-full_normal.jpg)
Construction of the Mutiara Line Penang LRT project is on track, according to the Mass Rapid Transit Corporation on Sunday.
MRT Corp, as the project’s owner stated that it has been actively advancing the Mutiara line Penang LRT project, with obtaining approval for advance works on April 15 being one of its main initiatives.
This comes after MCA vice-president Tan Teik Cheng voiced concerns about the project's seeming lack of physical progress despite its January groundbreaking, as reported by MalaysiaKini. -full_normal.jpg)
With 86 plots of land secured to date and gazetted ahead of the intended date of October 2025, the firm also emphasized that it has achieved great progress in terms of land purchases, assuring the public that the LRT Mutiara Line project is still on track and on schedule.
In addition, MRT Corp said that SRS Consortium Sdn Bhd, the main contractor for the first package of the LRT line, is fulfilling post-award conditions before issuing an official notice-to-proceed, emphasizing that utility relocation is a critical aspect of pre-construction work that must be completed before any station or viaduct-related construction can begin. 
The Mutiara Line, with an estimated cost of RM10 billion to RM13 billion, is considered the largest inland infrastructure project on mainland Penang. The 29.5 km elevated LRT line will have 21 stations, starting from the Silicon Island off Batu Maung. It will then pass through Weld Quay, its main interchange, the Penang Bridge, and end at the Penang Sentral transport hub in Butterworth.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRS2271
SELANGOR
BSU1401
JOHOR
JF384J
PULAU PINANG
PSF9490
PERAK
APL8039
PAHANG
CFH8716
KEDAH
KGJ3035
NEGERI SEMBILAN
NEM1410
KOTA KINABALU
SJU3520
KUCHING
QAB6589P
Last updated 30 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Public Review Opens for Revised Penang Mutiara LRT with Cross-Sea Link at Core
MRT Corp opens a three-month public review for the Penang Mutiara LRT, featuring a proposed six-kilometre cross-sea link to Penang Sentral.
23-02-2026
Penang Mutiara LRT Construction Kicks Off Jan 2026
Penang Mutiara Line LRT starts in Jan 2026, with traffic management measures ready to minimise disruptions.
19-11-2025
Penang Sentral Set to Become Mainland’s Integrated Transport Hub
The Butterworth KTM station, Mutiara Line LRT, and airport expansions will turn Penang Sentral into key transport and logistics hub.
11-11-2025
Penang Defends Mega Projects As Key To Tackling Traffic Woes
Penang’s transport councillor says flyovers, underpasses and the LRT are essential to ease congestion.
04-09-2025
MRT Corp Justifies RM16.8b Penang LRT Budget
MRT Corp says the RM16.8 billion ceiling for Penang LRT reflects market realities, but MCA wants clearer answers on taxpayers’ money.
21-08-2025
Langkawi LRT ‘Unrealistic’, Focus Stays on Penang LRT and ECRL - Loke
The government is pushing ahead with the Penang LRT and ECRL, but dismissed talk of a Langkawi LRT as unrealistic.
19-08-2025
Penang LRT Stays Within RM16 Billion Budget - MRT Corp
Penang LRT project capped at RM16 billion, with MRT Corp aiming to deliver a cost-efficient system despite rising expenses.
30-07-2025
Penang Still Waiting For Green Light From MOT For LRT project
Penang is set to begin Mutiara LRT construction but awaits final approval from MRT Corp and MOT.
02-07-2025
Latest News
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
Malaysia's First Locally Built EV And PHEV Pick-Ups Are Coming From JAC
JAC will locally assemble its T9 EV and PHEV in Kulim, creating Malaysia's first CKD electrified pick-ups, with exports also being explored.
29-09-2026
Nearly Half A Million Summonses To Foreign Drivers: JPJ Says Some Employers Are Enabling It
JPJ issued 481,119 summonses to foreign drivers from 2024 to Sept 2026, while warning that some employers and vehicle owners are enabling illegal driving.
29-09-2026
Why Is Malaysia's Finance Ministry Testing A GWM WEY G9? Here's What We Know
Malaysia's Finance Ministry is evaluating a locally assembled GWM WEY G9 PHEV with SPANCO. Here's what the government fleet trial actually means.
25-09-2026
Several Riders Skidded At The Same 'Anti-Skid' Lane. Here's What JKR Says
Several riders skidded on an 'anti-skid' Federal Highway motorcycle lane. JKR is investigating the surface, contamination and other possible factors.
25-09-2026
Only RM10K Separates The Two CKD iCAUR 03s - Here's What You Get
Both iCAUR 03 variants are now CKD in Malaysia. With just RM10,140 between the RWD and iWD, here's what the extra money gets you.
25-09-2026
JPJ Letting Rohingya Apply For Driving Licences? Here's The Fact Check
A viral post claims JPJ is proposing to let Rohingya apply for driving licences in Malaysia. JPJ says the claim is false and has reported it to MCMC.
24-09-2026
Going To Singapore From Oct 6? Check Your VEP Or Risk Getting Turned Back
Driving to Singapore from Oct 6? Foreign vehicles will face VEP checks during SG Arrival Card submission. Here's what Malaysian drivers need to know.
24-09-2026
Show More
trending_flat