Central Spine Road Connecting Pahang To Kelantan 63.35% Complete

As of July 10, 63.35% of the300 KM-long Central Spine Road (LTU) connecting the East Coast Expressway (LPT) junction in Bentong, Pahang, to Kuala Krai, Kelantan, has been completed.
Works Minister Datuk Seri Alexander Nanta Linggi reported a slight delay of 0.39% from the scheduled 63.74%, accounting for the approved extension of time (EOT). He however assured that all delays and challenges will be managed following best construction practices and current regulations.
To date eleven projects have been completed, fourteen are currently under construction, and one is in the procurement process.
![]()
Nanta also provided updates on the various packages of the project:
- Package 1: Kuala Krai to the Sungai Lakit Bridge, is 11.59% complete.
- Package 2: Sungai Lakit Bridge to Gua Musang, is 22.40% complete.
- Package 3: Gua Musang to Kampung Relong, is 84.25% complete.
- Package 4: Kampung Relong to Raub, is 63.69% complete.
- Package 5: Raub to Bentong has been opened to users.
- Package 6: Bentong to LPT Junction, is 30.07% complete.

He also highlighted the Ministry of Works' (KKR) plans to upgrade the East-West Corridor from Pasir Puteh, Kelantan, to Gerik, Perak, and from Simpang Pulai, Aring to Kenyir, Terengganu, under the 2030 Highway Network Development Plan (HNDP 2030).
Nanta mentioned that the Third Rolling Plan (RP3) and the Fourth Rolling Plan (RP4) under the 12th Malaysia Plan (RMK-12) for these projects have been approved. RP3 includes upgrading the route from Kampung Pak Badol to Kampung Banir Belikong in Pasir Puteh and replacement of two bridges in Jeli. RP4 involves upgrading the East-West Highway from Section 113 to Section 151 in Gerik, Perak.
Additionally, projects under the East Coast Economic Region Development Council (ECERDC) including the FT482 Pasir Puteh - Tok Bali route is under RMK-12 land acquisition.
Nanta was addressing a supplementary question from Nik Mohamad Abduh regarding KKR’s plans to upgrade the East-West Corridor, specifically from Pasir Puteh to Gerik and from Simpang Pulai, Aring to Kenyir, Terengganu.
Source: BERNAMA
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VSA4819
SELANGOR
BSV2920
JOHOR
JH7613J
PULAU PINANG
PSH5424
PERAK
APN2134
PAHANG
CFJ4636
KEDAH
KGJ9130
NEGERI SEMBILAN
NEM6571
KOTA KINABALU
SJV2938
KUCHING
QAB704Q
Last updated 23 Nov, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
KKR Seeking RM20 Million To Build R&R Along LTU Highway
Works Ministry seeks RM20 million budget allocation to set-up R&R along LTU Highway.
11-10-2024
Pahang Govt. Identifies Two R&R Locations Along The LTU Expressway
Pahang govt. identifies two locations along the LTU Expressway to house new R&Rs.
12-04-2024
LTU Section 5A: Raub Bypass Opens On Friday
The Section 5A: Raub Bypass of the Lingkaran Tengah Utama (LTU) Expressway opened last night, Friday, at 12:01
08-03-2024
Gua Musang Main Routes Closed For A Month For Lingkaran Tengah Project
The main entrances to Gua Musang were closed for a month beginning yesterday for the installation of bridge piles for the Lingkaran Tengah Utama Project (LTU).
31-03-2023
Two Million Road Users Set To Enjoy Toll-Free LTU
A total of two million road users are expected to enjoy the toll-free Lingkaran Tengah Utama (LTU) Expressway.
27-01-2023
Tolls Are Here To Stay. Minister Explains The Mind-Boggling Financial Nightmare Of Abolishing Them Completely
Works Minister Datuk Seri Alexander Nanta Linggi explains why abolishing tolls would cause a multi-billion ringgit financial nightmare for Malaysia, shifting crucial infrastructure funds away from schools and hospitals.
22-06-2026
50% Toll Discount Nationwide for CNY 2026
50% toll discount on selected highways from Feb 14–15 to ease CNY travel.
09-02-2026
Federal Highway Won’t Be Upgraded, Costs Deemed Too High
Despite worsening traffic conditions, the Federal Highway will not be upgraded, with the government citing high costs.
15-12-2025
Latest News
Women Want Female E-Hailing Drivers. But Are There Enough Options In Malaysia?
Looking for female e-hailing drivers in Malaysia? Explore women-only rides, service availability, passenger safety and legal transport requirements.
18-11-2026
Malaysia Toll Abolition Explained: RM400 Billion And Highway Concessions
Why could abolishing Malaysia's highway tolls cost RM400 billion? Explore highway concessions, toll payments and alternatives to nationwide toll abolition.
17-11-2026
GWM Malaysia 2026 Year-End Deals: Prices, Warranties And Financing Offers
GWM Malaysia's 2026 year-end deals include the ORA Good Cat from RM94,000, Haval H6 HEV privileges, WEY G9 financing and Tank SUV warranties.
16-11-2026
Honda Sumber Auto Edaran PJ Closes After 25 Years Of Operations
Honda Sumber Auto Edaran PJ has closed after 25 years, with over 27,000 cars sold. Here's what existing Honda customers should know.
16-11-2026
All-New Nissan X-Trail e-POWER x e-4ORCE Makes First Public Appearance In Malaysia
The new Nissan X-Trail e-POWER x e-4ORCE makes its first public road appearance in KL ahead of its Q4 2026 Malaysia launch. Here's what we know.
16-11-2026
Proton Sales 2026: Geely-Based Models Overtake Homegrown Cars
Geely-based Protons lead homegrown models in 2026 registrations. But the e.MAS lineup and Saga sales reveal a more interesting story.
13-11-2026
Johor Highway Upgrades: PLUS And Senai-Desaru May Open Early
Two Johor highway stretches on PLUS and Senai-Desaru may open early in 2027. Here's where they are, proposed dates and what drivers should know.
13-11-2026
Loke Says Some Welcomed His Resignation, Urges JPJ To Maintain Enforcement
Anthony Loke says some cheered his resignation, expecting JPJ's overloaded lorry crackdown to ease. Will enforcement continue without him?
12-11-2026
Show More
trending_flat
Malaysia First Used Car and EV Consignment Platform
This is the best place to sell your car at true market value. Instead of accepting low dealer trade-ins, we handle everything and connect your car directly to genuine buyers for the highest price.

Understanding CariCarzAutomall Consignment Plan


Approved 200-Check Points Inspection

7 Day Money Back Guarantee

One Year Extended Warranty

No Hidden Charge