Five LRT3 Stations Set To Be Operational In 2027

According to Transport Minister Anthony Loke, the five Light Rail Transit Line 3 (LRT3) stations that were previously cancelled should be operational by 2027.
He stated that these new stations' construction cannot be finished or put into service by the following year because it is not feasible to finish it in a year because the stations have not been constructed. "These are optional stations to be reintroduced, with implementation expected to take two or three years." He added.
The government will resurrect the plan to construct the five previously cancelled LRT3 stations, Tropicana, Raja Muda, Temasya, Bukit Raja, and Bandar Botanik. The project is estimated to cost RM4.7 billion, according to Prime Minister Datuk Seri Anwar Ibrahim, who made the announcement during the presentation of the 2024 Budget. 
Beginning on March 1, 2025, work on the LRT3 construction project in Klang, Selangor, will move from Bandar Utama to Johan Setia. This massive transportation project, which is expected to benefit two million residents, is expected to cost about RM16 billion.
Regarding the LRT3 project's status, Loke stated that as of December 25 of last year, it had reached 91.68 percent completion. The LRT Shah Alam line's scheduled launch date is March 1 of the following year.
Furthermore, the Rapid Transit System (RTS) Link construction, which connects Johor Baru and Singapore, is progressing well. Over 33% of the system aspect and 65% of the infrastructure have been completed. The full completion target is set for December 31, 2026, Loke stated.
Four kilometers of rail connect Bukit Chagar, Johor Baru Station, and Woodlands in Singapore. Of the three hundred fifty daily commuters who use the Johor Causeway, thirty-five percent are expected to use the RTS Link.
Regarding the Bandaraya station's repair status, Loke stated that work has been finished and is presently going through a trial phase by the Land Public Transport Agency (APAD). By the end of February, operations are anticipated to resume.
Prasarana funded the RM30 million repair work, according to Loke, adding that the company plans to take the contractor or project owner to court to hold them liable for the station's damages.

The Ampang LRT line experienced delays on January 27, 2018, as a result of a misaligned track near the Bandaraya LRT station. The viaduct's structural damage was ascribed to construction activities in the vicinity.
The route between Masjid Jamek and Bandaraya stations was temporarily closed by Rapid Rail as a result of this incident, forcing LRT passengers to choose buses or other alternate modes of transportation in order to get to their destinations.
-full_normal-full.jpg)
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRS2271
SELANGOR
BSU1401
JOHOR
JF384J
PULAU PINANG
PSF9490
PERAK
APL8039
PAHANG
CFH8716
KEDAH
KGJ3035
NEGERI SEMBILAN
NEM1410
KOTA KINABALU
SJU3520
KUCHING
QAB6589P
Last updated 30 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
LRT3 Hits 99% Completion - Loke
LRT3, which will connect Bandar Utama to Johan Setia, is 99% complete and on track for launch, says Transport Minister.
30-07-2025
LRT 3 Will Cost RM9.7 Billion Less Despite 5 Key Station Reinstatement
LRT 3 will cost RM9.72 Billion less even with the reinstatement of five key stations compared to initial 2015 cost quoted.
29-10-2024
Federal Highway Lane Closure For LRT 3 Project Construction Works
Federal Highway sees lane closures to facilitate the LRT 3 project works from July 26 to July 28.
24-07-2024
LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug
LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).
24-08-2023
LRT Service Will Resume At 6 Stations On May 12 , 6Am
Stesen Bandaraya, Sultan Ismail, PWTC, Titiwangsa, Sentul, and Sentul Timur LRT services will resume on May 12th at 6 a.m.
11-05-2023
Ten LRT KJ Line Stations Set for Upgrade – Open From 9 AM on Weekends
Ten LRT stations on the Kelana Jaya line will be upgraded, and their operation times will be affected on weekends.
28-07-2025
Rapid KL On-Demand Adds 5 New Zones — Cyberjaya & Putrajaya Included
The Rapid KL On-Demand service has been expanded to five new zones, including Cyberjaya and Putrajaya.
17-06-2025
Rapid KL Boosts Peak Hours Operations Ahead of ASEAN Summit
Rapid KL extends peak hours train frequency to support commuters during the ASEAN Summit.
21-05-2025
Latest News
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
Malaysia's First Locally Built EV And PHEV Pick-Ups Are Coming From JAC
JAC will locally assemble its T9 EV and PHEV in Kulim, creating Malaysia's first CKD electrified pick-ups, with exports also being explored.
29-09-2026
Nearly Half A Million Summonses To Foreign Drivers: JPJ Says Some Employers Are Enabling It
JPJ issued 481,119 summonses to foreign drivers from 2024 to Sept 2026, while warning that some employers and vehicle owners are enabling illegal driving.
29-09-2026
Why Is Malaysia's Finance Ministry Testing A GWM WEY G9? Here's What We Know
Malaysia's Finance Ministry is evaluating a locally assembled GWM WEY G9 PHEV with SPANCO. Here's what the government fleet trial actually means.
25-09-2026
Several Riders Skidded At The Same 'Anti-Skid' Lane. Here's What JKR Says
Several riders skidded on an 'anti-skid' Federal Highway motorcycle lane. JKR is investigating the surface, contamination and other possible factors.
25-09-2026
Only RM10K Separates The Two CKD iCAUR 03s - Here's What You Get
Both iCAUR 03 variants are now CKD in Malaysia. With just RM10,140 between the RWD and iWD, here's what the extra money gets you.
25-09-2026
JPJ Letting Rohingya Apply For Driving Licences? Here's The Fact Check
A viral post claims JPJ is proposing to let Rohingya apply for driving licences in Malaysia. JPJ says the claim is false and has reported it to MCMC.
24-09-2026
Going To Singapore From Oct 6? Check Your VEP Or Risk Getting Turned Back
Driving to Singapore from Oct 6? Foreign vehicles will face VEP checks during SG Arrival Card submission. Here's what Malaysian drivers need to know.
24-09-2026
Show More
trending_flat