ECRL Project, Aims to Operate by 2027
Recently, Prime Minister Datuk Seri Ismail Sabri Yaakob has officiated a ceremony to mark the start of Genting Tunnel excavation under the East Coast Rail Link (ECRL) first tunnel boring machine (TBM1) project.
The project costs more than 50 million and could enhance connectivity between Selangor and the east coast states including transport cargo from Port Klang to Port Kuantan.
Apart from that, it benefitted young people especially 5,000 youths from east coast as it has the potential to produce more highly skilled locals through ECRL Industrial Skills Training Programme (PLKI-ECRL).

Tunnel Boring Machine (TBM1) is predicted to complete approximately 2 and a half years to three years to break through 16.39km Genting Tunnel which costs an average excavation amount of between 400m and 600m per month.
Once the tunnel project is accomplished, it will become the longest rail tunnel in the South-east Asia region which expected to operate in January 2027 having 665 kilometres distance across Kelantan, Terengganu, Pahang, and Selangor.
More uniquely, this tunnel excavation is the only among 59 tunnels drilling to use the TBM method, compared to the drilling and blasting methods for previous tunnels.
-full.jpg)
With a speed of 160kph, the journey is more convenient and safer for passengers to travel to the east coast.
Total of 20 stations, consisting of 10 passenger stations and a mix of passenger and cargo stations, the ECRL is also connected to the LRT Kelana Jaya Line at ITT Gombak, thus reducing travel time to Kelantan to 4 hours compared to 7 to 12 hours of journey during festive season.
TBM1 is a state-of-the-art machine built made for this project and is the largest rail construction machine in South-east Asia to convey through Titiwangsa Range along the Bukit Tinggi area which link Bentong with Gombak, Selangor.
THE East Coast Rail Link (ECRL) is under the partnership project between Malaysia Rail Link Sdn Bhd (MRL) and China Communications Construction Co Ltd (CCCC).
Tagged:
Written By
Jesica Sendai
from 9 to 5 grinder to 'racing' her way in the automotive industry through editorial work.
JPJ Running Numbers
KUALA LUMPUR
VRS2271
SELANGOR
BSU1401
JOHOR
JF384J
PULAU PINANG
PSF9490
PERAK
APL8039
PAHANG
CFH8716
KEDAH
KGJ3035
NEGERI SEMBILAN
NEM1410
KOTA KINABALU
SJU3520
KUCHING
QAB6589P
Last updated 30 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
Latest News
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
Malaysia's First Locally Built EV And PHEV Pick-Ups Are Coming From JAC
JAC will locally assemble its T9 EV and PHEV in Kulim, creating Malaysia's first CKD electrified pick-ups, with exports also being explored.
29-09-2026
Nearly Half A Million Summonses To Foreign Drivers: JPJ Says Some Employers Are Enabling It
JPJ issued 481,119 summonses to foreign drivers from 2024 to Sept 2026, while warning that some employers and vehicle owners are enabling illegal driving.
29-09-2026
Why Is Malaysia's Finance Ministry Testing A GWM WEY G9? Here's What We Know
Malaysia's Finance Ministry is evaluating a locally assembled GWM WEY G9 PHEV with SPANCO. Here's what the government fleet trial actually means.
25-09-2026
Several Riders Skidded At The Same 'Anti-Skid' Lane. Here's What JKR Says
Several riders skidded on an 'anti-skid' Federal Highway motorcycle lane. JKR is investigating the surface, contamination and other possible factors.
25-09-2026
Only RM10K Separates The Two CKD iCAUR 03s - Here's What You Get
Both iCAUR 03 variants are now CKD in Malaysia. With just RM10,140 between the RWD and iWD, here's what the extra money gets you.
25-09-2026
JPJ Letting Rohingya Apply For Driving Licences? Here's The Fact Check
A viral post claims JPJ is proposing to let Rohingya apply for driving licences in Malaysia. JPJ says the claim is false and has reported it to MCMC.
24-09-2026
Going To Singapore From Oct 6? Check Your VEP Or Risk Getting Turned Back
Driving to Singapore from Oct 6? Foreign vehicles will face VEP checks during SG Arrival Card submission. Here's what Malaysian drivers need to know.
24-09-2026
Show More
trending_flat